Wednesday, May 8, 2019

Bridge Continued


At the end of week 1 the foundations were poured along with a temporary slab to build the first precast arch on..





Here is the temporary slab with plywood nailed down and the first arch form in place.


The rest of the interior forms..


The first rebar cage. There was another cage tied later that is not shown. 



The first arch was poured at the end of week 2. That was a 15 hour day and I did have some help from a friend. I have been working 2-3 long days per week on the bridge




2 more pours to go!